Main Project Plan
This is the first version of my project plan and is just an estimation. The project lasts twelve weeks and represents my diploma's final work.
Project's specifications and tasks' time-line
This is a time-line defined during the 9th week of the project. It lists the project's specifications and tasks in the implementation's phase. The project's specifications where *delimited* according to indications received from Sebastien Barre.
Note: These specifications only reflect the contribution of Juan Carlos Bermúdez to the KWWidgets UI-Desinger project as his final diploma work, thus not ALL of the project's specifications are included.